Client: Medway NHS Foundation Trust

Type of work: Refurbishment of existing Pembroke Ward

Site address: Pembroke Ward, Medway Maritime Hospital,Windmill Road,Gillingham, Kent ME7 5NY

Refurbishment Works to Pembroke Ward, Medway Hospital

The Project

Refurbishment of existing Pembroke Ward including:new suspended ceiling, fire safety works to walls, fire alarm, access control, emergency lightings, complete rewire, new flooring, new fire doors/frames, works related to fire stopping and fire strategy decoration, white rock PVC wall cladding.

Refurbishment Works to Pembroke Ward, Medway Hospital

How We Solved The Problems

After consultation with the Estates Department and ward staff a solution was agreed and a phased handover was initiated.Approximately 70% of the ward was handed over as a fully functioning ward on the 24th December 2024. The remaining area was partitioned off for safety so the final building works in this area could be completed. This required new site access routes, splitting services and close liaison with the ward to ensure no disruption. Phase 2 was handed over on the 30th January 2025 on time and on budge