Client: Mid and South Essex NHS Foundation Trust
Type of work: Refurbishment of Cancer treatment room
Site address: Southend Hospital, Prittlewell Building, Prittlewell Chase, Westcliff-on-Sea, Southend-on- Sea, Westcliff-on-Sea SS0 0RY
Cancer treatment room Refurbishment Works
The Project
The works were undertaken within an existing patient recovery area, located directly opposite another active cancer treatment room. Patients receiving treatment were often critically unwell, so their comfort, privacy and ability to recover peacefully were key considerations throughout the project.
- Strip out of existing finishes and structural alterations for new doors
- Supply and install new lead lines door sets
- New flooring, white rock and decorations
- New kitchenette units and work top
- Fixtures and finishes throughout
- New reception desk to main area
Cancer treatment room refurbishment Works
Challenges Overcome
Careful planning and close coordination with hospital staff were central to the successful delivery of these works. Noisy activities were scheduled to minimise their impact on patients and neighbouring clinical areas, with regular communication maintained with departmental staff throughout the project.
- The main challenge was carrying out this work directly next to another active cancer treatment room that was located across the corridor, which required frequent pauses to allow critically ill patients to recover in peace.
- We were able to deploy additional resources to complete heavier tasks, such as installing new lintels, during the brief periods when the adjacent room was unoccupied. Additionally, we had to revise our approach to installing the new shower because the existing under croft was confirmed to contain asbestos throughout. We changed the design from a wet room to a slimline shower tray. This allowed the waste pipe to achieve sufficient height without running through the under croft, while maintaining a minimal step into the shower area.