Client: University of Hertfordshire

Type of work: Refurbishment

Contract Type: MTC JCT

University of Hertfordshire – Refurbishment of Teaching Rooms

Description of the Project

  • Enclose and secure working area
  • Strip out existing 3 rooms, including floors, ceilings and electrics
  • Form new walls and doors to suit new layout
  • Replace suspended ceiling tiles and grid
  • Make good and paint existing Crittall windows with new roller blinds
  • New lights and containment dor power/data ect.
  • Redecorate room complete
  • Level and New carpet tile floor covering
  • Leave clean and clear for UH staff to do AV connections

University of Hertfordshire – Refurbishment of Teaching Rooms

Challenges Overcome

To ensure efficiency and continuity, we proposed practical adjustments such as the substitution of specified materials for locally sourced and more readily available alternatives, reducing lead times and maintaining programme momentum.

This approach also allowed us to reallocate resources from other projects and ensure that an appropriately skilled workforce was available to deliver the works within the agreed timeframe.

Throughout the duration of the project, we closely monitored variations and design developments, holding regular on-site meetings with stakeholders to ensure alignment, transparency, and satisfaction with progress and direction.