Client: University of Cambridge
Type of work: Education Refurbishment
Site Address: Jeffrey Cheah Building, Puddicombe Way, Cambridge CB2 0AW
Jeffrey Cheah Building – Replacement of high level glazing unit
Description of the Project
Following a report of a broken glass panel at the Jeffrey Cheah Building at the University of Cambridge, we were instructed to attend site urgently and make the area safe. Our team carried out an initial inspection, documented the damage, and installed a temporary plywood boarding solution to provide immediate protection.
We then engaged a specialist glazing subcontractor to replace the panel using a crane lift. Prior to the works, we collaborated with the University’s structural engineer to undertake ground assessments and confirm the suitability of the crane setup.
To minimise disruption and risk, the replacement was completed out of hours on a Saturday. The University’s Head of Health & Safety attended the works, while our site team established a secure exclusion zone using Heras fencing around the crane and work area below. Abseil technicians removed the damaged glass panel, which was lowered safely to ground level by crane. The replacement panel was then lifted into position and sealed by the abseilers, successfully completing the installation.
Jeffrey Cheah Building – Replacement of high level glazing unit
Challenges Overcome
Complex working-at-height operations, coordination of specialist subcontractors, crane ground-bearing assessments, and stakeholder engagement with the University’s structural engineer to ensure a safe and compliant installation.